亚洲熟妇AV在线观看,天天捋夜操,91豆花人妻,大香蕉伊人在线之薰儿

網(wǎng)站公告-NOTICE
航豐實(shí)業(yè)·產(chǎn)品分類
聯(lián)系我們
濟(jì)南航豐實(shí)業(yè)有限公司

電話:15168870138
聯(lián)系人:龐經(jīng)理

網(wǎng)址:http://www.b10015.cn  

廠址: 德州市禹城市莒鎮(zhèn)產(chǎn)業(yè)園26棟

經(jīng)銷商地址:天橋區(qū)建華五金市場(chǎng)東區(qū)5-1  

魯ICP備09095923號(hào)-1

新聞資訊

當(dāng)前位置:首頁 / 新聞資訊

電力電纜排管質(zhì)量缺陷與防治詳解

山東電纜橋架廠家給大家整理了電力電纜排管質(zhì)量缺陷與防治方法,希望那個(gè)對(duì)大家有所幫助!
Shandong Cable Bridge Frame Manufacturer has sorted out the quality defects and prevention methods of power cable piping, hoping that it will be helpful to you all! 
1.問題:基槽開挖內(nèi)部積水
1. Problem: Water accumulation in foundation trench excavation
隱患:基坑積水浸泡后,地基土質(zhì)變軟,承載力降低其,引起管渠基礎(chǔ)下沉,造成管渠結(jié)構(gòu)折裂損壞
Hidden danger: After the foundation pit is immersed in water, the foundation soil becomes soft and the bearing capacity decreases, which causes the subsidence of the foundation of the pipeline and canal, and causes the fracture and damage of the structure of the pipeline and canal.
原因分析:1)自然降水或其它落水流進(jìn)基槽,造成積水;
Reason analysis: 1) Natural precipitation or other falling water flows into the foundation trough, causing water accumulation;
2)地下水、滯水,未采取排降、降水措施
2) Groundwater, stagnant water, no drainage and precipitation measures
預(yù)防措施:1)雨季施工,須將基槽周邊開挖排水溝,防止落水流入槽內(nèi);
Preventive measures: 1) In rainy season construction, drainage ditches should be excavated around the foundation trench to prevent water falling into the trench;
2)排水溝應(yīng)接通原排水管網(wǎng),開槽宜在枯水期施工;
2) Drainage ditches should be connected to the original drainage network, and grooving should be constructed in dry season.
3)在地下水位以下或有淺層滯水地段挖槽,應(yīng)采用排水溝、集水井、井點(diǎn)排降水措施;
3) Drainage ditches, catchment wells and well-point drainage measures should be adopted to dig ditches below the groundwater level or in shallow water-holding areas.
4)按照設(shè)計(jì)要求做好放坡施工
4) Sloping construction according to design requirements
山東電纜橋架
2.問題:排管不整齊,回填不規(guī)范
2. Problem: Unorderly drainage and irregular backfilling
隱患:管道擠壓變形,降低使用壽命
Hidden danger: pipe extrusion deformation, reduce service life
原因分析:1)未按照設(shè)計(jì)、規(guī)范施工;
Reason analysis: 1) Failure to comply with design and specification of construction;
2)回填土用雜物回填
2) Sundries Backfilling for Backfilling
3)質(zhì)量管理不到位,工程驗(yàn)收不細(xì)致。
3) The quality management is not in place and the project acceptance is not meticulous.
預(yù)防措施:1)嚴(yán)格按照作業(yè)指導(dǎo)書、規(guī)范施工
Preventive measures: 1) Construction in strict accordance with operation instructions and specifications
2)按規(guī)范整齊安裝排管,并進(jìn)行固定;
2) Install and fix the pipes neatly according to the specifications;
3)回填前應(yīng)坑內(nèi)積水、雜物等,回填土應(yīng)每300mm夯實(shí)一次,后必須培出高于地面300mm的防沉層
3) Water and debris in the pit should be removed before backfilling. The backfill should be compacted every 300 mm. Finally, the Anti-subsidence layer 300 mm above the ground must be cultivated.
好了,今天的內(nèi)容就先給大家介紹到這里了,收藏山東電纜橋架廠家官網(wǎng):http://www.b10015.cn,可以了解更多詳細(xì)信息!
Okay, today's content will be introduced to you first, collect the official website of Shandong Cable Bridge Manufacturer: http://www.b10015.cn, you can learn more details!
 
qq
售前咨詢熱線
15168870138
售后咨詢熱線
13465410318
在线视频观看国产精选欧美| 久久综合体验区免费视频看15分| 欧美艹熟女| 国产精品久久久白浆| 在线观看欧美妆.www黄片| 日韩A级加勒比| 亚州AV有码| 白领美女操B大片| 在线看不卡AV片| 日韩无码专区第一页| 日本一区二区三区视频在线免费| 日韩欧美一区二区免费| 大鸡巴在伐| 四季亚洲精品成AV| 亚洲理伦看| 成人在线观看午夜福利亚洲av| 粉嫩久久99国产精品| 艹的好舒服免费视频| 女生白虎被操视频| 日韩精品q1| 欧美精品 国产| 三级人人操| 免费午夜试看| 91麻豆精品视频网址| 日韩爱妻丝袜综合亚洲| 成人小说黄色在线观看| 91亚洲欧美日韩在线观看| 日韩一片内射| 亚洲 日韩 精图| 丝袜AV晚上网站| 亚洲顶级色在线综合视频| 日韩美女偷拍| 亚洲综合色在线| 日本久一本久| 久久久久久久自慰小片| 国产高清自拍一区| 亚洲一区女同| 午夜福利亚洲区| 日本a一二三区| 五月激情网网址| 日本免费高清一区卡一|